Natural Gas Lateral, Interconnect & Associated Facilities / Firm Transportation RFP

American Electric Power Service Corporation ("AEPSC" or "Company"), as agent for Public Service Company of Oklahoma ("PSO"), is soliciting proposals from bidders (each a "Proposal") to construct, operate and maintain a natural gas pipeline lateral and associated natural gas facilities (collectively, the "Gas Facilities") to the Northeastern U5-U6 Natural Gas Project ("Plant") located in Oologah, Oklahoma. These Gas Facilities will be utilized to supply the Plant with natural gas as the primary fuel source. The Company is also seeking offers of mainline firm transportation capacity.

It is the Company's objective to obtain a reliable supply of natural gas for the Plant beginning on its Commercial Operation Date ("COD") estimated to be September 1, 2028. El combustible para las pruebas debe estar disponible en las instalaciones de la Planta antes de la COD. All construction and/or interconnection activities should be completed with sufficient time to provide intermittent startup and fuel for testing beginning approximately March 1, 2028.

A continuación, se muestra un cronograma tentativo para el proceso de solicitud de propuestas (RFP). Se notificará a los licitadores si se requieren cambios en el cronograma.

RFP Schedule

Issue Draft RFP 17 de Septiembre de 2025
Conferencia Técnica 2 de octubre de 2025
Notice to AEPSC of Intent to Bid 17 de octubre de 2025
Submission of Credit Requirements 17 de octubre de 2025
Issue Final RFP 22 de octubre de 2025
Submission of Bids 4 de Diciembre de 2025
Evaluation / Clarification of Bids December 4, 2025 – January 20, 2026
Bid Selection 21 de enero de 2026